Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.

AIntegration

BTime

CPlanning

DCommunication

正确答案

来源:www.examk.com

答案解析

该题的关键词较多,不过都是并列的关系,包括"ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition、 projectinformation"。其主要语句结构为"Project()Management(主语)is(谓语)the Knowledge Area",含义为"项目什么管理是知识领域",后续的定语从句说明该知识领域的特点。其实根据关键词"Proj ect information"考生可以很容易识别出来应该是项目沟通管理。

相似试题

  • (单选题)

    The()provides the project manager with the authority to apply organizational resources to project activities.

    答案解析

  • (单选题)

    The most crucial time for project risk assessment is ( ).

    答案解析

  • (单选题)

    ()means that every project has a definite beginning and a definite end.

    答案解析

  • (单选题)

    In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

    答案解析

  • (单选题)

    The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

    答案解析

  • (单选题)

    Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

    答案解析

  • (单选题)

    The()defines the phases that connect the beginning of a project to its end.

    答案解析

  • (单选题)

    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

    答案解析

  • (单选题)

    Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

    答案解析

  • (单选题)

    The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.